The following information presents the results of project analysis performed for the Congestion Management Program (CMP). Projects are scored based on various metrics derviced from the model (e.g., change in volume).
The two tables below presents the point categories and possible values. Note that transit mode share is only applied to transit projects.
| Performance Measure | Increase | No Change | Decrease | New Road | Cong Road |
|---|---|---|---|---|---|
| Change in V/C Ratio | 0 | 2 | 5 | 3 | |
| List of Congested Roadways | 1 | ||||
| Transit Mode Share | 3 | 1 | 0 | ||
| VMT | 0 | 1 | 2 | ||
| VHT | 0 | 1 | 2 | ||
| VHD | 0 | 1 | 2 |
| Volume Increase | Points |
|---|---|
| No Increase | 0 |
| 1 - 499 | 1 |
| 500 - 999 | 2 |
| 1000 - 1499 | 3 |
| 1500 - 1999 | 4 |
| 2000 - 2499 | 5 |
| 2500 - 2999 | 6 |
| 3000 - 3499 | 7 |
| 3500 + | 8 |
| Model ProjID | Project Name | Project Description | Length | Current Lanes | Future Lanes | Cost (000s) | Score |
|---|---|---|---|---|---|---|---|
| 19 | Kamehameha Highway | Widening | 1.90 | 3 | 4 | 160,300 | 16 |
| 32 | Makakilo Dr | New Location | 2.48 | 0 | 4 | 83,900 | 15 |
| 111 | Central Mauka Road Second Access | Added Capacity | 16.19 | 0 | 4 | NA | 14 |
| 25 | Kapolei Parkway | Widening and Extension | 1.28 | 0 | 4 | 53,000 | 13 |
| 102 | H-1 Widening Waipahu Off-Ramp | Added Capacity | 0.23 | 1 | 2 | NA | 13 |
| 103 | H-1 University Avenue Interchange On/Off Ramp Modifications | Realignment | 0.41 | 1 | 1 | NA | 13 |
| 105 | Kunia Road Widening | Added Capacity | 6.28 | 2 | 4 | 348,900 | 13 |
| 112 | Wahiawa Second Access | Added Capacity | 3.25 | 0 | 2 | NA | 13 |
| 115 | Roosevelt Extension | Added Capacity | 0.29 | 0 | 2 | NA | 13 |
| 4 | Fort Barrette Road | Widening | 1.25 | 2 | 4 | 50,000 | 12 |
| 5 | Fort Barrette Road | Widening & New Location | 0.28 | 2 | 4 | 13,200 | 12 |
| 29 | Kualaka’i Parkway | Widening | 2.36 | 4 | 6 | 180,000 | 12 |
| 107 | Likelike Highway Widening | Added Capacity | 0.49 | 4 | 6 | NA | 12 |
| 113 | Waianae Second Access | Added Capacity | 4.85 | 0 | 2 | 1,269,000 | 12 |
| 120 | Kunia Road Widening | Added Capacity | 0.37 | 5 | 6 | NA | 12 |
| 124 | Farrington Highway (short) | Widening | 0.70 | 4 | 6 | 34,500 | 11 |
| 30 | Kualakai Pkwy Extension | New Location | 0.35 | 0 | 4 | 20,000 | 11 |
| 31 | Kualakai Pkwy Extension | Widening | 0.35 | 0 | 2 | 180,000 | 11 |
| 110 | Puuloa Road Widening | Added Capacity | 0.69 | 3 | 5 | NA | 11 |
| 41 | East-West Arterial | New Location | 3.88 | 0 | 2 | NA | 10 |
| 42 | UHWO Roads | New Location | 2.68 | 0 | 2 | NA | 10 |
| 122 | Kahekili Highway | Widening | 3.32 | 2 | 4 | NA | 10 |
| 2 | Farrington Highway | Widening | 7.20 | 4 | 6 | 252,000 | 9 |
| 22 | Kamokila Boulevard | New Location | 0.65 | 0 | 4 | 28,700 | 9 |
| 24 | Kapolei Interchange Complex Phase 2 | Interchange | 0.43 | 0 | 1 | 139,000 | 9 |
| 104 | H-1 HOV Median Lanes | Added Capacity | 4.97 | 0 | 2 | NA | 9 |
| 106 | Kunia Interchange Improvements | Added Capacity | 0.05 | varies | varies | 160,000 | 9 |
| 34 | Moanalua/Kamehameha Off-Ramp | Widening | 0.47 | 2 | 3 | NA | 6 |
| 33 | Makakilo Mauka Frontage Road | Frontage Road | 0.54 | 0 | 1 | 18,200 | 3 |
Each link below provides detailed information for a single project.
Project 2
Project 124
Project 4
Project 5
Project 19
Project 22
Project 24
Project 25
Project 29
Project 30
Project 31
Project 32
Project 33
Project 34
Project 41
Project 42
Project 102
Project 103
Project 104
Project 105
Project 106
Project 107
Project 110
Project 111
Project 112
Project 113
Project 115
Project 120
Project 122